What's next for Cherry Creek Shopping Center in Denver, CO? 2026 brought new stores and a cleared west end.

Cherry Creek Shopping Center went through 2026 as two projects at once, one refitting the mall that stayed open and one clearing its western edge for a new neighborhood.

In February 2026, Simon announced more than $250 million in work at three of its malls, and Cherry Creek Shopping Center in Denver, Colorado, was one of them.

The two-level enclosed mall at 3000 East First Avenue, about 1.1 million square feet with Nordstrom, Neiman Marcus, and Macy's as anchors, had come under Simon's direct management after the company acquired Taubman's interests.

The plan called for work on flagship spaces, storefronts, and the mall's architecture, with construction to begin during the year.

New storefronts, moves, and a canceled launch

The tenant shuffle started early.

Captain Crepes opened in February, and SKIMS arrived on February 17.

In March Gucci moved into a larger store.

Ash & Agave, a restaurant built around the food of Mexico's coast, opened in early April in the space California Pizza Kitchen had held.

BYLT Basics and Swarovski relocated in April and May, H&M reopened a renovated store on May 21, and lululemon moved into a bigger space the next day.

One launch went wrong.

On Saturday, May 16, 2026, the release of the Swatch and Audemars Piguet Royal Pop drew a crowd that turned disorderly; one of the doors was damaged before police cleared the area.

Swatch canceled the release and kept its boutique closed through Sunday.

Speculation pinned the crowd on resellers chasing a profit, and talk of arrests spread, though none were made.

The store reopened on Monday, May 18, and sold out of the new watch that day.

The west end comes down for Cherry Creek West

West of the enclosed mall, 13 acres of the property belonged to a separate project, Cherry Creek West, led by East West Partners and its partner Ascentris.

Parking closures began in February 2026, and after a demolition ceremony on March 10, crews started on the freestanding buildings that had held Elway's, the western Container Store, and an earlier Macy's Furniture Gallery.

The former Bed Bath & Beyond building was kept for project use, its demolition put off to the second phase.

By late May more of the west-end buildings had been razed.

In April 2026 the developers opened leasing for One Cherry Creek, an eight-story building at First Avenue and Clayton Street with 200,000 square feet of offices and about 19,000 square feet of shops.

In November they announced that crews would start shoring the ground and digging in early December across nearly half the site, the official groundbreaking for a first phase of about 400 homes, offices, and shops over a two-level underground garage.

The whole district, with an estimated cost of about $1.8 billion, is planned to hold more than 800 homes, 12 percent of them income-restricted, and more than 2,000 underground parking spaces.

Underground work is scheduled through summer 2027, first residents and office tenants for late 2029, and the second phase for completion in summer 2033.

Crate & Barrel arrives as Arhaus plans a move

On the east side, Macy's folded its furniture business into its main store by April 2026, freeing a freestanding showroom of about 23,000 square feet.

Crate & Barrel took it and held a grand opening on October 1.

Milk Jelli, a bath-and-body shop, and STUDS, a piercing and jewelry studio, were announced in June and opened during the year.

In September Arhaus was named among the tenants of The Oasis Apartments, a new building at 299 Milwaukee Street, with its move set for early 2027.

By October Pottery Barn was planning a store in the roughly 13,400-square-foot Arhaus space, with about $1.3 million set aside to rebuild it, and plans to renovate the inside of the Hollister store were approved.

The Cherry Creek Fresh Market ran on the mall's east side on Saturdays from May to October.

The mall is open through the holidays, with Santa photos until December 24.

Arhaus still trades in the space Pottery Barn is waiting for, Rothy's is due on May 28, 2027, and the Fresh Market returns on May 1, 2027.

Some visitors reportedly noticed a gap between the newest luxury storefronts and older-looking stretches of the mall.

On the west side the old buildings are gone, and the cleared ground waits for excavators due in early December.

Independent Publisher Notice

BestAttractions is an independent editorial publisher. We are not affiliated with, endorsed by, or acting on behalf of any location, business, property owner, manager, government agency, or organization described in this article. Comments posted on this page are not forwarded to, reviewed by, or acted upon by any entity mentioned in the article. For official inquiries, complaints, applications, bookings, or other requests, please contact the relevant entity directly through its official website or other verified channels.